Thursday, August 28, 2014

Tee Project 8-28

We now have 2 holes, 5 & 6, that are roughed in and have the general shape of our new tees.  The crew will continue on the holes 3 & 7 this week

After the rough grading is done the irrigation crew follows with our new irrigation heads.  Once the irrigation is installed they will be adding 2' of sand to each tee surface, that sand will be mixed into the top 2' of topsoil.  End result will be a 50% sand / soil mixture on the new tee areas.

The final steps will be finish grading / seeding or sodding.  There will be one tee box sodded on each hole.  This will give us one tee to be playable very soon.


Above is a picture of the irrigation being installed on #6 Tee.

Have a good Day !!